AssetWise CONNECT Edition Help

To Complete an Activity Program Task

Follow these steps to complete a task on an activity program.
  1. Open the program for which you want to complete a task.
  2. Select the task that you want to complete.
  3. From the Work Task menu, select Complete. For example,

    The Task Complete Work Task dialog appears.

  4. Do one of the following:

    If there is only one work task then

    • from the Assignee list, select either the default task skill group or a specific user
    • enter a Due date by clicking the calendar icon ( ), and selecting a date
    • enter any Task instructions in the box.

    or

    If there are parallel tasks then:

    • select a parallel task from the list
    • accept or edit the task question
    • in the Answer box, select either Yes or No in response to the parallel task question
    • from the Assignee list, select either the default task skill group or a specific user
    • enter a Due date by clicking the calendar icon ( ), and selecting a date
    • enter any Task instructions in the box.

  5. Click Verify and complete.
The task is completed and the workflow advances to the next task.